CINDY STAATS OF SAFEGUARD SPOTSY ON DATA CENTERS IN SPOTSYLVANIA
By John Williams, Editor, The Spotsylvania Gazette
Cindy Staats is the founder and director of Safeguard Spotsy, a grassroots coalition of Spotsylvania County neighbors advocating for responsible data center development. John Williams interviewed her by phone on Saturday, November 28, 2026.
Talking with Cindy Staats is a reminder of what community organizing should be about — neighbors coming together to ask questions and push for answers.
Q: What is Safeguard Spotsy — who is in it, and how did it start?
A: We are a grassroots coalition of neighbors that have come together to advocate for responsible, and community informed and led development in the county. We got our start in June of this year, 2026. My husband and I attended the community meeting that the Crossroads developer, Kettler, was hosting, and we came out of that meeting really nervous about what was happening in the community. Because there was no opportunity to ask questions. There was no one that we could see that even was identifiable as the developer to even go up and ask questions to.
And so we went up that weekend to a Protect Stafford meeting. And we came out of that meeting and said, that's what we need to do here in Spotsy. That's what we need. What Aaron has done with Protect Stafford is quite extraordinary. And I wanted to kind of create something similar here in this county. And so literally that weekend, I formed the Facebook group. And then I had quite a few people contact me and were interested in helping, and so we kind of went from there, really.
Currently, we are now a registered 501 C4 nonprofit. I have two other people that sit on my board, so it is me and Kelly Schaefer and Trelane Birlar. So we all sit on the board and then we have kind of this core group of volunteers as well that help us and attend our community meetings and pass out literature and things like that.
Q: What does responsible, limited data center development mean, in practice, for Spotsylvania?
A: I think it's something we're still trying to figure out, right? Because for Safeguard Spotsy's reasons, I don't think that we're siting them in the right locations, right? Putting the data center in the middle of a residential community is not responsible, in our opinion. I think there could be better locations. Where exactly that is? I don't know. We need to figure it out.
I just don't understand why the county insists that we must approve these centers within a certain time frame. I think the impression that a lot of residents have, me included, is that the county seems to be kind of steamrolling these data centers in because I think they live under this fear that if they don't approve them quickly, that they will go away, that the developers will be like, you know what, we don't have time, we can go somewhere else. And I think the county needs money. And they see data centers as a quick way to make money for the county, right? But I don't think that they're taking the proper due diligence and understanding the long term ramifications of these types of developments, right? Nor do I think that the county as a whole is considering the long term ramifications of the regional development of these data centers, right?
I think responsible development is maybe pausing at this point. I think we need to pause and figure out, okay, we have nine approved campuses right now in Spotsylvania alone. We need to stop and figure out what that looks like for us in 10 years. What does that mean? What is it going to do to the river? What is it going to do to our power grid? Are we going to be experiencing rolling brownouts next year, like PJM suggests that we might, right? And maybe during that pause, the county can really take a hard look at what land we have. And where these types of developments should go if — and if we should even continue approving more data centers. I personally don't think we should. I think nine is enough for our county.
And I think, because the county made such a bad tax deal with Amazon, they have put themselves in this position that they feel like, and this is personal opinion, that maybe they feel the county has to approve more of them in order to get more tax revenue because we won't be bringing in the tax revenue that we could have been bringing in because the board, the previous board approved such a bad tax deal for the county. It's bad for the county. Great for Amazon.
Q: The Board of Supervisors approved the Crossroads Technology Campus data center on November 17, 4-3. What happened at that vote, as you saw it?
A: My opinion is this. Kettler, the developer of Crossroads, has a standing appeal, currently, they still have not dismissed this appeal for vested rights. And the county knows this. The county took that vote, knowing that there is outstanding issues in front of the Board of Zoning Appeals. And I think they voted in a way thinking that if they did not approve this SUP, the county is going to get sued. That's what I think happened. And I think we have a certain number of board members that are pro data center, as evidenced by their voting records, right? But I think there's other board members that voted a particular way out of fear of being sued.
I know a lot of residents feel very betrayed by Lori Hayes with her vote, because in a lot of their view, she was the deciding vote. I don't know if that's true or not. I understand why it looks that way, because it was a 4-3 vote.
And I think Lori, being a Lee Hill resident — I am a Lee Hill resident — and I think Lori tried to do what she thought was the best option for residents, knowing that this appeal is out there, right? So if Kettler wins vested rights in this appeal, then they would have gotten a by-right build, right? And there would be no conditions placed on the build, on the development. So I think in her mind, she was doing what was the best option for her district. Whether or not that is true is different, right? But I don't think she went into it, and I don't feel that she voted for this development because she likes the development. I think she voted for the development to prevent what she thought could be a bad development.
Q: You said after the vote that the board should have deferred a decision until it had more information. What information was missing?
A: There's a lot of holes in this SUP. Number one, the development that they approved, the SUP that they just approved, is not reviewed under the current plan, right? So the timeline is just a little wonky, for lack of a better word. The Planning Commission voted yes for the development on September 16th, and then the board approved a new comprehensive plan, October 27th, and then Crossroads submitted a new GDP, new narrative statement, new documents, on October 30th, but they all still reference the old comprehensive plan, not the current plan that was adopted three days before their paperwork. So that really should have been looked at. Because some things in the comprehensive plan changed that would make this project no longer in accordance with the comprehensive plan. So that's one.
Number two, the sound study, quote unquote, that they submitted is actually just a sound assessment, which, by state law, that is what is required, but in the comprehensive plan, it now states that a sound study must be conducted. But the sound assessment that was submitted was on a project that was submitted multiple versions ago. It is not a sound assessment for the current plan of development that was approved, if that makes sense.
And then, you know, the county waited until the very last minute to upload their generator testing conditions. For many days before the hearing, it just said, generator testing condition placeholder. And now there's all of this generator testing, but I don't think they really understand what generator maintenance, what does that look like? How long do they have to run maintenance? There's no limit on noise. So if they're doing maintenance, there's going to be like 283 or 87 generators on this project. That's a lot, right? And I don't feel like they really understood what that means.
And then we don't really understand whether or not, is there water capability for Crossroads? Because their letter, where they received a 1,000,000 gallons a day allocation, was dated December 31st of 2025, or I should say it would remain in effect until December 31st, 2025. And then there's no further confirmation that the water is available, right? So we don't have confirmation about water. There has to be a separate water agreement created with the county. Why does the public not get access to that? That hasn't even been drafted. There's studies that claim to have been done, you know, years ago, but none of that was available for the public to look at. We're talking geotechnical studies, blasting — budgets were there, but none of these things are mentioned in this SUP. So if they can do blasting, is it still required? I don't know because the project isn't the same. So we don't have answers to those questions. We have a school that's, you know, 1,200 feet away, and are we doing blasting in the middle of the day when students are trying to learn? At Lee Hill Elementary. So these are questions that I think the public deserved answers to before this project was approved.
Q: What changed between the Planning Commission recommendation and the Board of Supervisors decision on Crossroads?
A: The Planning Commission voted yes on September 16th, and then the board approved a new comprehensive plan on October 27th, and then Crossroads submitted a new GDP, new narrative statement, and new documents on October 30th, but they all still reference the old comprehensive plan, not the current plan that was adopted three days before their paperwork. Some things in the comprehensive plan changed that would make this project no longer in accordance with the comprehensive plan.
Q: You said you were disappointed but not dissuaded, and were exploring avenues for residents to appeal the Crossroads decision. Where does that stand?
A: I am looking into what options there are. The biggest issue in terms of an appeal, I think, would be the fact that this other issue of this appeal is still sitting out there, right? Kettler's appeal is still active and still scheduled to be heard December 15th. They have not dismissed it. Why the county did not write into their SUP that that appeal would have been dismissed upon approval of an SUP, I don't understand. That is like basic legal 101, right? And that is very concerning to me because what happens if Kettler continues with this appeal? And what if they win? I don't think they will. I think their appeal is very — I don't think it's very strong. But I am absolutely looking for avenues in which potentially residents would have some level of recourse for what has happened.
Q: You said you had begun research on the Fredericksburg Digital data center application. What have you found so far, and what are the concerns there?
A: There's not a whole lot there. They filed their special use permit for a data center. So this project, Fredericksburg Digital, again, is very similar. I believe it was already zoned industrial land. So this project would go in basically kind of in the same area as Powerhouse 95, Cosner, that area. And so they have this SUP, which is, you know, this SUP application. It's a one-page document, or essentially one page, and then it outlines some fees and costs. So you don't get a ton of information from that. And then they do have a GDP submitted. It would be fairly close to the apartments that would back up to it. And then, you know, I still have to go through their development narrative. That's the other thing, which is on my schedule for today.
It would be directly behind those apartments. Do you know where Spotsylvania Hospital is? If you follow Spotsylvania Parkway, all the way to the end, there are those apartments that sit there and then there's like the Sheetz gas station. It would be directly behind those apartments.
And thinking about how many — there are what, three other projects right there? If this project gets approved, I believe this one is looking at 1,100,000 square feet of data center buildings. And then Cosner, I believe, is like 2,000,000. Summit Technology is another one that just put in paperwork. And I think that would either be one or two million. We're talking one, two, three, four, five, potentially seven to eight million square feet of data center buildings, literally in one very small square space, right? And I know the Stafford project that is going in across the river that is coming up for vote, I understand that that's getting a ton of attention because of the size of that project. But I need people to also understand that these projects here are roughly the same size, in terms of square footage of data centers, right? If this is seven or eight million, isn't King's Corridor around 11,000,000, is that right?
And these are literally right in the middle of all of these residential areas. Across the street is Lee Hill, we're talking Crossroads Baptist Church is across the street. We've got the hospital, we've got apartments. What are we doing?
I think one of the big issues with the county is my understanding is that the way Lee Hill development happened was all of that land was at one time zoned industrial and rural, right? And then it slowly became Lee Hill and was so residential, encroached on industrial land. But the county uses that as saying, well, it was already zoned industrial. Like we can't do anything about it. And I'm like, okay, but the county also chose at some point to allow this area to become a residential area. Therefore, they now need to look at that and say, okay, maybe we should not be approving industrial projects since we've already allowed residential projects.
Q: In September you named noise pollution as Safeguard Spotsy's top concern, followed by air pollution and water usage. What does each of those mean for the people living near a data center?
A: For air pollution, again, I think we need — okay, so we're requiring Tier 4 generators. That's great. But there's no requirement for air pollution testing. Nowhere in the SUP does it say that we have to test what our air quality is. And again, the issue being, one campus might be okay, but we have nine, right? And they're all within a very, very concentrated area, but there's no requirement for testing to know what our air quality is like now versus what is our air quality when one, two, three and then all nine are up and running. Why are we not requiring air testing?
You got diesel generators, you got projects close to homes, you got elementary school, churches, hospitals. Hospitals with, you know, NICU units. This does not seem responsible to me at all.
Q: Safeguard Spotsy has also raised wetlands, diesel generators, and projects close to homes, an elementary school, and churches. What should people in the county know about those?
A: We have nine approved campuses and now we have nine more that are going through rezoning and potentially could become data center campuses, right? That would be 18 campuses in Spotsylvania, in a roughly 15-mile area? And these projects have massive demands for electricity, for water. And we don't really have a comprehensive understanding of what these cumulative impacts are going to be, right? What happens to our watershed? There's a DEQ permit hearing coming up in December about wetlands that are going to be destroyed on one of the campuses. This is happening on every single campus.
Q: What is Safeguard Spotsy asking the county to do next, and what are you asking residents to do?
A: I want the county to stop approving data centers. I want them to pause and allow what they have approved to come up. We can't do anything about these campuses now. They are approved. The county needs to stop approving data center development until we can understand the ramifications of the projects they have already approved.
I think it's really important that the public, that our residents, our citizens, become engaged in the issue, engaged in understanding what is happening in our county, what kinds of projects are being approved, and what those potential ramifications are. I think it's important that residents contact their leaders and voice — we are not saying, and we're not advocating, that we're not for technology, right? It's about responsible growth.
I would really, really, really like to see the county pause at this point. Allow us to see what all of this development that they have approved, what that's going to do to our county. Crossroads, you know, Amazon paid or is paying for this reuse system to be upgraded. But Crossroads, the project they just approved, is going to cap that water use. So essentially, we allowed Amazon to come in, upgrade our reuse system for themselves. For themselves. Maybe in 30 years when these buildings become obsolete and they're all vacant, great, the county can have that water then, but what does our water quality look like? Do we have water? What happens to the river? We don't know. And they are approving these projects without consulting experts to understand what these ramifications are and what the cumulative impacts of this many projects in this small of a space is going to do to residents, to the county as a whole. I just don't understand what the rush is.
Q: Is there anything else about Safeguard Spotsy, or about data centers in Spotsylvania, that you would like people to know?
A: I'd really love to see more young people get involved in this issue. We need to get everybody involved as much as possible.
More News from Spotsylvania Courthouse
- FEDERAL FUNDING FOR VRE EXPANSION: $729 MILLION FOR LONG BRIDGE AND PHASE 2 FEDERAL FUNDING FOR VRE EXPANSION: $729 MILLION FOR LONG BRIDGE AND PHASE 2
- THE DEAL BEHIND VRE'S EXPANSION: VIRGINIA AND CSX, 2019 THE DEAL BEHIND VRE'S EXPANSION: VIRGINIA AND CSX, 2019