Spotsylvania supervisors approve Crossroads data center campus in 4–3 vote
Spotsylvania supervisors approve Crossroads data center campus in 4–3 vote
SPOTSYLVANIA COUNTY, Va. — The Spotsylvania County Board of Supervisors voted 4–3 Tuesday, Nov. 17, to grant a special use permit for the Crossroads Technology Campus, a 555-acre project in the Lee Hill District near Lee Hill Elementary School. The vote authorizes the data center use. The developer must still secure site-plan and permit approvals before crews can clear land or begin building.
Supervisors Deborah Frazier, Lori Hayes, Tim McLaughlin and Drew Mullins voted for the permit. Supervisors David Goosman, Jacob Lane and Chris Yakabouski voted against it, according to GoFredericksburg’s account of the roll call.
RCK Digital Crossroads LLC applied to build seven data center buildings and three electrical substations north of Mills Drive (U.S. 17) and west of Benchmark Road. The 555 acres cover the entire property. In its application, the developer said it would keep the residentially zoned portions as buffers between the campus and neighboring properties.
What must happen before construction begins?
Construction traffic and emergency access. For families near Lee Hill Elementary, one question is whether construction trucks will use the school road. The developer’s August 26 filing said construction traffic would stay off Lee Hill School Drive. It also called for a plan to manage construction impacts before final site-plan approval for each phase. During each site-plan review, the developer said it would submit an emergency action plan to the county fire department so first responders could assess access and prepare for emergencies. These commitments appear in the August filing. The Gazette has yet to verify the language of the final permit conditions.
Soil and drainage. The filing called for testing how readily water drains into the ground at each proposed stormwater facility. It also called for an investigation into whether excavation could expose acid-producing soils. If those soils are found, the filing requires the developer to submit a plan explaining how crews would handle the material and protect nearby streams and groundwater.
Clearing and building permits. Under county rules, crews need a land-disturbance permit and a preconstruction meeting before clearing or grading can begin. A clearing permit covers work only within approved boundaries. Construction of the data center buildings requires a separate building permit.
Why Safeguard Spotsy asked supervisors to delay the vote
Before Tuesday’s vote, FXBG Advance published Safeguard Spotsy’s draft executive summary of its objections. The group asked supervisors to postpone their decision. It raised two questions in particular: Had residents had a chance to comment on the plan supervisors were voting on? And did the sound study tell neighbors what they could expect to hear from that version of the campus? Read the draft executive summary in FXBG Advance.
The Planning Commission recommended approval on September 16. According to Safeguard Spotsy, the October 30 development plan changed building locations and sizes, the layout of substations, open space and setbacks. The group said the commission had not held a public hearing on those revisions. It also pointed out that the county adopted a new comprehensive plan on October 27, three days before the revised application narrative, while the applicant continued to cite the previous plan. The group asked supervisors to identify which version they were evaluating.
Safeguard Spotsy also questioned the noise projections. The sound study modeled eight buildings on four parcels, while the proposal before supervisors called for seven buildings. At one location, the study predicted nighttime sound levels right at the proposed limits. The group also said the study did not evaluate the cooling equipment the developer might use if reclaimed water were unavailable. The Gazette had previously documented the difference between the layout used in the sound study and the later development proposal.
For nearby families, another practical question was when backup generators could be tested. Safeguard Spotsy said the draft condition it reviewed still contained a placeholder for generator testing. It asked supervisors to establish enforceable testing restrictions and require a sound study based on the revised layout before granting the permit.
The Spotsylvania Gazette contacted Safeguard Spotsy on Wednesday, Nov. 18, for its reaction to the vote.
More News from Spotsylvania Courthouse
- Who is Safeguard Spotsy? The residents’ group behind the Crossroads challenge Who is Safeguard Spotsy? The residents’ group behind the Crossroads challenge
- Former Stafford Supervisor Monica Gary withdraws from Virginia Senate race Former Stafford Supervisor Monica Gary withdraws from Virginia Senate race